Keystone dredging wraps up in December

Dredging is expected to last for nine weeks.

A massive sediment-scooping project at the Coupeville ferry terminal that began last month is on schedule to be completed by the third week of December.

Every three to five years, Keystone Harbor is dredged by the U.S. Army Corps of Engineers. The engineer formation built the artificial harbor in 1947 and 1948 and has been maintaining it ever since.

The dredging is necessary to clear the path for the ferries to enter the harbor.

Dredging began Oct. 12 and will last for nine weeks.

Accumulated sediment is scooped from the harbor much like a toy is scooped from an arcade claw machine, explained Public Affairs Specialist Dallas Edwards.

A clam-shell dredge is used to transport the 50,000 cubic yards of materials to a site further up the beach.

According to an Army Corps of Engineers fact sheet, the dredge material is determined to be suitable for beneficial placement to nourish an eroded section of the beach near the breakwater.

Work is being done between 9:10 p.m. and 6:45 a.m. in order to avoid interruptions to the Coupeville-Port Townsend ferry route.

A press release stated that a temporary gate was installed. During the dredging, if a boat needs to be launched, the gate is opened.

The project has been coordinated and approved by the Army Corps of Engineers, Washington State Department of Ecology, Washington State Department of Transportation and Washington State Parks.

No impacts to wetlands, biological resources or water quality are expected.

More in News

COVID-19 outbreak being investigated at Regency

18 people have tested positive for coronavirus at a long-term care facility in Oak Harbor.

Oak Harbor resident Charles Ringer testifies in his defense in a child rape trial that ended in a jury deadlock. Photo by Jessie Stensland / Whidbey News Group
Complex child rape trial ends in deadlock

The judge delacred a child rape case involving a retired Navy pilot from Oak Harbor a mistrial.

South Whidbey Elementary students collecting food for Good Cheer

A donation barrel will be in the lobby of the K-4 school campus until Dec. 16.

Superior court trial rescheduled because of COVID exposure

A domestic assault trial was delayed after a defense attorney was exposed someone with COVID-19.

Despite COVID-19, ferries could be busy on Thanksgiving

Although essential-only travel is urged, Washington State Ferries cautions people catching a… Continue reading

Photo provided
Langley Library Manager Vicky Welfare stands at the corner of the access ramp to the library entrance. Pending state budget approval, Sno-Isle Libraries is planning to improve building access inside and out.
Langley Library due for makeover, pending approval of state budget

Sno-Isle Libraries is tentatively moving forward with plans to remodel and update… Continue reading

Parks, Rec receives OK for Trustland Trails

South Whidbey Parks and Recreation District is moving ahead with proposed trails… Continue reading

Woman injured in accidental shooting files lawsuit

The woman needed both legs amputated above the knee and has filed a lawsuit for damages.

Woman charged with murder in fatal stabbing

A woman who stabbed her partner during a Nov. 13 power outage has been officially accused of murder.

Most Read